Spring 2018

Kenyon College Storage Facility is Underway

The Kenyon Storage Building is coming out of the ground as the 20,000 square foot slab was recently completed.  Activities on the site at this point include, storm, sanitary, building steel, underground electric and communications and all equipment procurement are all occurring as we target the mid-summer completion date for the project.  Thanks to the Lincoln crew and our subcontractors as they had the unfavorable weather conditions of January and February to schedule around to get the project to this point!

 

 