Spring 2021

Progress is Being Made on the Health & Wellness Complex

The 119,000 square foot Health & Wellness Complex at Muskingum University is proceeding nicely with the perimeter foundations and poured concrete walls being completed this past month, all while enduring winter site conditions. The structural steel is slated to begin in the Spring. The main elevator tower was also topped out within the past several weeks.

The 2nd and 3rd quarter of 2021 should see the main frame and building envelope enclosure along with placing interior floor slabs for the field level, concourse, first and second floors along with the athletic field house. 

Construction began in summer 2020 on the complex with completion scheduled for fall of 2022.

 